Register before May 20 for a Chance to Win One of 3 Microsoft - Surface Laptop Go - 12.4" Touch-Screen ...Register

Breakout C:
Modular Data Centers: Maximizing Scale and Speed to Market through Integrated Design

Tuesday, June 14, 3:30 PM – 4:30 PM

The presentation includes a case study featuring innovation in action during the final months of design and construction of SoFi Stadium, the NFL’s newest stadium and home to two professional football teams. This case study is hosted by the lead architect and MEP designer and includes a discussion and graphic presentation following the design, manufacturing and assembly of the data center, which was fabricated off-site in Houston, TX, including all MEP systems in place, and delivered to Inglewood, CA for final assembly. The project was successfully executed between September 2019 and May 2020, during the Covid-19 pandemic.

Jon Benson (bio)
Director of Modular Innovation
TAS Energy, Inc.

Matt Lamont, AIA, LEED, AP (bio)
Mission Critical Team Leader, North America
HKS, Inc.